Welcome to Scheduling Fundamentals

6 min Free preview

In this lesson

  • Know what the course covers and how each lesson is built
  • Know the conventions used in every lab
  • Map the course's terms to Primavera P6 and Microsoft Project

The dates in a good schedule are not typed in. They are calculated from three things: the activities, how long each one takes, and how they depend on each other. Change any of the three and the dates move. This course is about that calculation, the Critical Path Method (CPM), and about reading what it tells you.

You don’t need any scheduling experience. If you already use Primavera P6 or Microsoft Project, expect to find out why the software puts the dates where it does.

How the course is organised

ChapterWhat you’ll do
1. Getting startedLearn the lab and its conventions
2. DependenciesTie activities together with the four relationship types, lags and leads
3. The Critical Path MethodRun the forward and backward pass, and find the critical path
4. FloatUse total and free float, and recover negative float against a deadline
5. Wrap-upBuild a schedule from a logic table, then take the knowledge check

Each lesson follows the same pattern: a short explanation with a worked example, a lab where you make the change yourself, and review questions. The lab tasks check themselves, so you know when you’ve got it right.

Conventions used in every lab

  • Durations are in working days. The working week is Monday to Friday, with no holidays.
  • Day 1 is the first working day of the project. Every lab project starts on Monday 2 November 2026.
  • Activity IDs step by 10 (A1000, A1010, A1020…) so there is room to insert work later. That is a common habit in real schedules.
  • Behind the scenes, CPM counts time in working days from the project start. Lesson 3.1 explains the numbers the lab shows as ES, EF, LS and LF.

What you need

A current desktop browser and a screen about 1280 pixels wide. Nothing to install, nothing to book. Your lab work is saved in your browser; use File › Save project file if you want a copy.

Same ideas, different words

You don’t need P6 or Microsoft Project for this course. If you use one of them, this table maps the terms:

This coursePrimavera P6Microsoft Project
ActivityActivityTask
Relationship (FS, SS, FF, SF)RelationshipDependency or link
Lag (negative lag = lead)LagLag (lead time)
Total floatTotal FloatTotal Slack
Free floatFree FloatFree Slack
Schedule (F9)Schedule (F9)Calculates automatically by default
Start no earlier thanStart On or AfterStart No Earlier Than
Finish no later thanFinish On or BeforeFinish No Later Than

Ready? The next lesson is a tour of the lab. It takes ten minutes, and everything after it builds on it.